Notice of Closure - 2nd Line Bridge Replacement
R.W. Tomlinson Limited would like to advise residents and business owners of the following road closures.
2nd Line Road Bridge Girder Erection:
- County Road 2 full closure at 2nd Line Road - Tuesday July 23, 2019 from 7:00 am to Wednesday, July 24, 2019 at 5:00 pm. Traffic will be detoured on local roads.
- In the event of inclement weather, the closure will be postponed 7 days. The full closure would then occur from Tuesday, July 30, 2019 to Wednesday, July 31, 2019.
All consideration has been given to implement traffic control measures to ensure minimal disruption to the traveling public. We apologize in advance for this inconvenience and very much appreciate the public's patience during construction.
Please follow @Ontario511 for further information on construction and closures.